Cost of Keystone XL Pipeline In South Dakota More Than Doubles

Reuters reports that “the cost of the South Dakota portion of TransCanada Corp’s Keystone XL pipeline has more than doubled to $1.974 billion in the last four years the project has awaited federal approval, the company said in a petition filed with the state Public Utilities Commission on Monday.”  

The leap in costs from the previous 2010 estimate of $921.4 million is due to factors including the protracted regulatory process, inflation, currency changes, labour cost increases and materials storage, TransCanada spokesman Shawn Howard said.”  

“The project to build the 1,179 mile (1,900-km) pipeline to carry 830,000 barrels per day of Canadian crude from Alberta’s oil sands to the Gulf Coast, is in its sixth year of waiting for a U.S. permit after running into fierce environmental opposition.”

Recent Stories

Supreme Court airs concerns over Oregon city’s homelessness law

Supreme Court to decide if government can regulate ‘ghost guns’

Voters got first true 2024 week with Trump on trial, Biden on the trail

Supreme Court to hear oral arguments on abortion and Trump

House passes $95.3B aid package for Ukraine, Israel, Taiwan

Senate sends surveillance reauthorization bill to Biden’s desk